IMPORTANT INFORMATION TO CONTRACTORS AND OWNERS

CONCERNING THE PENNSYLVANIA UNIFORM CONSTRUCTION CODE

 

48 HOUR NOTICE IS REQUIRED PRIOR TO SCHEDULING OF ANY INSPECTION

CALL 814-929-5138 OR 814-781-3663 TO SCHEDULE OR TO REQUEST AN INSPECTION

NOTE:  Only footer inspections will be given a specific appointment time.

 

The following information will be required when calling, if necessary please leave a message:

 

bullet

Name Of Property Owner

bullet

Location of Property to be inspected

bullet

Phone number where you can be reached

bullet

Type of Inspection

bullet

Day or Time of Week Inspection is requested

 

REQUIRED INSPECTIONS

 

NOTE:  Many of these required inspections can be conducted at the same time. The Building Official may require additional inspections, as necessary, to assure compliance with the Code.

 

FOOTER INSPECTION: A footer inspection is required after forms have been erected or trenches cut and any required reinforcement steel is in place.  THIS INSPECTION MUST TAKE PLACE PRIOR TO SCHEDULING CONCRETE FOR THE SITE.

 

FOUNDATION INSPECTION:  This inspection is required after the footer / foundation is completed, french drains are installed and waterproofing is applied.  Also an inspection of the subbase and vapor barrier of the basement floor is required at this time. This inspection is required prior to backfilling taking place. 

 

STRUCTURAL FRAMING INSPECTION:  When all structural framing is completed and prior to placement of insulation and any covering of walls takes place. The framing inspection is not complete until the electrical, plumbing, and mechanical rough-in inspections are completed.

 

ELECTRICAL, PLUMBING, MECHANICAL INSPECTIONS: A rough-in inspection must be conducted prior to covering any of these building components with insulation or wall coverings.  A final inspection of these items will be done during the Final Inspection process.

 

ENERGY INSPECTION:  This inspection is required at some point prior to the covering of any required insulation materials.

 

WALLBOARD INSPECTIONS:  This inspection is required after drywall, or other material, is installed and prior to covering the installation of any wallboard materials.

 

SANITARY INSPECTIONS:  Inspections of connections to a public sewer or inspections of an on-lot septic system are performed independently by the local Municipal Sewer Authority or by the Sewage Enforcement Officer.

 

FINAL INSPECTION:  This inspection is made after the building is completed and final electrical, plumbing, energy, mechanical, and sanitary inspections are verified. 

 

 

CERTIFICATE OF OCCUPANCY:  A CO will only be issued after an acceptable Final Inspection and when the construction site has been cleared of all debris and construction waste and equipment.  Final grading of the site must also be completed. A CO may be issued for a portion of a residential building, if the portion independently meets Code requirements.

 

OTHER IMPORTANT CODE REQUIREMENTS:

 

CHANGES TO BUILDING PLANS:  As with any construction project, plans and ideas will change as the project progresses. However, any change to the approved building plans SHALL HAVE ADVANCED WRITTEN APPROVAL BEFORE ANY CHANGE TO THE ORIGINAL PLANS OR WORK MAY TAKE PLACE.

 

STOP WORK ORDERS:  Upon notice from the Building Official or Inspector that work on any building is being done contrary to approved plans,  to the provisions of the Code or in a unsafe and dangerous manner, such work must be immediately stopped.   Any person who shall continue such work shall be subject to penalties as provided by law.

 

PLACEMENT OF PERMIT AND CONSTRUCTION DOCUMENTS:  The Building Permit shall be located in a visible location and shall be kept on the site of the work until the final completion of the project.  A set of approved construction documents shall also be kept on the site of the work, and available to the Building Official until the final completion of the project.

 

INTERPRETATIONS:  By law, the Building Official / Inspector has the power to render interpretations of the Code.  However, such interpretations must be in conformance with the intent and purpose of the code.  It is very possible that Code Officials in various municipalities may render different interpretations of the same requirement.  Any interpretation of the Code maybe appealed to the municipal Appeals Board.  A nominal fee is charge to file an appeal.

 

RESPONSIBILITY: By law, the Municipality and any Building Official or Inspector acting in good faith and without malice cannot be held liable for any liability or damage accruing to persons or property as a result of any act or omission in the discharge of official duties.  The builder or individual who actually committed the violation of the Code is the responsible party; this is usually the contractor.  It is the duty of every person who performs work, for which the Code is applicable, to comply with the requirements of the International Building Codes and the Pa. Uniform Construction Code.

 

RIGHT OF ENTRY:  The Building Official or Inspector has the right to enter property at reasonable times to perform inspections or when reasonable cause exists that violations of the Code exist on the property. If entry is refused, the Official shall have recourse to the remedies provided by law to enter the property.

 

CONSTRUCTION & DEMOLITION WASTE:  All waste generated by construction must be properly disposed of.  BOTH STATE AND LOCAL LAW STRICTLY PROHIBIT THE BURNING OF ANY CONSTRUCTION OR DEMOLITION WASTE.

 

TOILET FACILITIES FOR WORKERS:  The Code requires that all construction sites have toilet facilities available to workers.  Typically a portable toilet can be rented and installed temporally at the construction site.  A Permit is not required to install this type of unit.

 

THESE REGULATIONS ARE NEW AND CAN BE VERY CONFUSING.  IF YOU ARE IN DOUBT ABOUT ANY CODE REQUIREMENT, PLEASE CALL AND ASK!